Quick Turnaround Hangar Solves Urgent Aircraft Repair Mission

IMG_0651

Quick turnarounds and airplane hangars are two of the many areas of expertise in Sunbelt Rentals' wheelhouse. That's why an international aircraft maintenance service called on them to help get a grounded plane back in the air FAST.

The privately-owned plane routinely transported its owner, a respected millionaire entrepreneur, around the country. But on a recent flight, the pilot reported landing gear issues and requested immediate clearance to land at a small regional airport. The landing proved uneventful, but the plane was grounded until the landing gear issue could be investigated and repaired.

The small regional airport didn't have a hangar large enough to house the plane. This situation left the aircraft on the ground (AOG) team leading the project with a big problem to solve. They needed a temporary maintenance hangar large enough to protect the plane and work crew during repairs.

The team conducted research and identified Sunbelt Rentals' expertise in the installation of airplane hangars for clients such as the U.S. Air Force, Coastguard, and the president's Marine One helicopter fleet.


The Challenge

The AOG team faced a strict deadline. They were feeling pressure from the owner who wanted his plane returned to its home base airport and the regional airport that wanted the aircraft’s space on its tarmac vacated as soon as possible. These circumstances led the AOG team to request the completion of the installation within 10 days after the start date.

The AOG team requested a large enclosed hangar. The dimensions of the plane required a space that was about one-third of an acre in size. The hangar needed to close out the elements, especially wind, while the aircraft was being repaired. The space had to allow enough height and width for the mechanics to lift the plane on the jack to replace its landing gear.


The client’s structure needed:

1200ft-hanger-1
     
mercedes-icon-rev001-07

Personnel doors

mercedes-icon-rev001-11

Safety features

mercedes-icon-rev001-12

Airplane cargo door
     


Additionally, Sunbelt Rentals' project manager learned that the airport would not allow the team to stake into the tarmac, so they had to devise a way to stabilize the structure.


The Solution

Sunbelt Rentals' expert team considered the client specifications carefully. They chose the MTS™ as the ideal solution for the temporary maintenance hangar, based on the dimensions of the plane and the request for a durable, fabric structure capable of keeping the wind from getting under the plane. They chose concrete ballasts as their anchoring platform, to avoid drilling stakes into the tarmac.

The MTS™ structure is engineered to be quickly installed for temporary or permanent projects. Engineered using the standard peaked-arch profile, the Sunbelt RentalsTension Series. has proven its versatility on projects ranging from sports facilities to permanent warehouses.


Sunbelt Rentals' solution included the following features:

  • Sunbelt Rentals Tension Series™, 13,564 sq. ft.
  • 4 personnel doors
  • 4 fire extinguishers
  • 4 exit signs
  • 1 magnetic cargo door
  • 30 LED lights
  • 120 Concrete Ballasting blocks (3,500 lbs)

 

Expediting delivery of 120 concrete ballasts to the job site required Sunbelt Rentals' project manager to do some logistical planning–he needed to find a local vendor with sufficient trucks to transport the ballasts to meet the strict deadline. Once the vendor was secured the installation team deployed.

The crew arrived on-site at the appointed time and began assembly of the frame for the structure. Despite advance planning and crew clearance, the project was unexpectedly delayed by the Federal Aviation Authority (FAA) demanding a specific permit. The crew had been granted airport clearance to install the structure, but the airport’s management overlooked a necessary FAA permit. The Sunbelt Rentals team was required to stop working until the permit could be obtained. Fortunately, they were able to expedite the permit from the usual six-week process to only one week.

The Sunbelt Rentals team was able to resume work. In a few days, the plane rolled into the hangar as planned. Sunbelt Rentals' installation team then enclosed the gables and began the finishing touches to complete the installation. The AOG mechanics were so anxious to start repairs that they started working on the plane as Sunbelt Rentals finished the install.

Sunbelt Rentals' team completed the project on-time, as promised, with the aircraft repairs well underway.


The Result

IMG_0655-2Two days after the hangar was complete, the plane was ready to fly. Sunbelt Rentals' solution enabled the AOG team to complete their mission in just a few days and deliver on their promise to the plane's owner to return his aircraft safe and sound to its home base.


The Takeaways

When a plane is grounded, it's a logistical problem for the airport team and the AOG team responsible for the maintenance and repairs necessary to get the plane back in service. That’s when you need a partner who offers flexible, customizable solutions and brings aviation industry and logistical expertise to the table.

If you have a time-sensitive project, choose a vendor partner with a proven track record in providing quick turnaround solutions. Choose Sunbelt Rentals'.

Call one of our project managers today.

Get Started

Topics: Aircraft Hangars